CONSTRUCTION TIMETABLE

Work begins
Week of May 5, 2008

Excavation
Summer '08–Spring '09

Core construction
Spring '09– Summer '10

Shell construction
Summer '09–Spring '11

Interior build out
Summer '09–Summer '12

Site work
Spring '11–Spring '12

Opening

Summer 2012

Construction on Ann & Robert H. Lurie Children's Hospital of Chicago, opening June 2012, continues on schedule thanks to the skill and dedication of more than 500 workers currently on-site.  Our top priority on the job site is safety for the workers and the community, and we applaud our team’s commitment to frequent safety briefings, thorough safety orientations, adherence to the strictest safety regulations and recommendations and daily stretching exercises.